Home Page > Monthly Update > Property transactions.

Home Page
Contact
Editorial Team

Boundaries and adverse possession.
Business lease renewal.
Co-ownership and estoppel.
Easements.
Landlord and tenant (general).
Long leases.
Mobile homes.
Mortgages.
Nuisance and trespass.
Planning.
Property litigation and ADR.
Property transactions.
Public access to land.
Residential tenancies.
Restrictive covenants.

Current page






Property transactions.

The editors of this section of the site are Peta Dollar, solicitor who works as a freelance lecturer, trainer and writer (peta@petadollar.co.uk) and Alex Troup, barrister at St John's Chambers Bristol.

Overage

Reasonable endeavours


Gaia Ventures Limited v Abbeygate Helical (Leisure Plaza) Limited
[2018] EWHC 118 (Ch)


Summary

The trigger date for payment of overage occurred just after the longstop date, so that no overage was payable. The Court awarded damages to the seller’s successor in title, holding that the failure to achieve the trigger date before the longstop date was due to the purchaser not having used reasonable endeavours to achieve various property transactions as soon as reasonably practicable.




Facts

The case concerned an overage clause in a 2003 transfer of a long lease of a commercial property in Milton Keynes which provided that within 10 days of a ‘Trigger Date’ an ‘Additional Payment’ of £1.4M would be due (“the Overage Provision”).

The Trigger Date would occur upon the grant of satisfactory planning permission, subject to Abbeygate having obtained the necessary variations of (or the vesting in itself and merger of) various leases so that the development permitted by the planning permission could take place. The Trigger Date was subject to a 10-year longstop provision.

Abbeygate covenanted to “use its reasonable endeavours to obtain” the planning permission and there was also an obligation on Abbeygate to “as soon as it considers strategically advisable (taking into account the requirement to obtain an Acceptable Planning Permission) commence and thereafter use reasonable endeavours to negotiate and agree with the parties entitled to the reversions…the [necessary] variations…as soon as reasonably practicable”.

The development process for the site was complex, involving two planning permissions, the second of which was amended more than once. Eventually, a satisfactory planning permission was obtained and Abbeygate also reached agreement to acquire the superior leasehold reversion and some further land.

Abbeygate had considerable influence over when and in what order conditions in the various agreements were satisfied so that they could control the onward transactions to ensure that the end transaction (acquisition of the supermarket within the development by an institutional investor) funded all of the transactions. However, there was a tension between the flexibility that Abbeygate had obtained via these conditions and their obligations to use "reasonable endeavours" to achieve particular outcomes "as soon as reasonably practicable” as part of the Overage Provision. In fact, completion of the transactions (and the conditions required to fulfil the Overage Provision) did not occur until 4 days after the Longstop Date.

Issues

Gaia alleged that Abbeygate had failed to use reasonable endeavours, particularly in relation to the last few months leading up to the Longstop Date.

Decision

Mr Justice Norris identified no fewer than seven issues which he had to determine to see whether Gaia’s claim should succeed, six of which turned on questions of interpretation, particularly as to ‘reasonable endeavours’ and ‘as soon as reasonably practicable’.

He found that Abbeygate did not in the last months leading up to the Longstop Date make reasonable endeavours to achieve as soon as reasonably practicable the variations in the property interests required by the Overage Provision; and that if reasonable steps had been taken as soon as reasonably practicable, all necessary property interests would have been in hand sufficiently early for the Trigger Date to fall before the Longstop Date. He held that Gaia was entitled to damages in the sum of £1.4M (plus interest).
    “The simple truth is that what lay behind this approach was not a desire to take steps as soon as reasonably practicable but a desire to leave things as late as possible to ensure that the [supermarket agreement] remained conditional until funds were released by [the institutional investor]. If matters had been driven by a desire to do things as soon as reasonably practicable it is highly probable that by mid-February a specifically enforceable agreement for a variation (and it is probable that a completed Deed of Variation) would have been in place.
    For these reasons I find and hold that Abbeygate did not after 31 October 2012 make reasonable endeavours to achieve as soon as reasonably practicable the variations in the property interests contemplated by…[the] Overage Provision…. I further find and hold that if reasonable steps had been taken as soon as reasonably practicable all necessary property interests would have been in hand (in accordance with…the Overage Provision) …[so that] the Trigger Date would have fallen at a time that entitled Gaia to claim the overage payment. I therefore hold that Gaia is entitled to damages in the sum of £1.4 million.” (Paras 109 and 110)
Norris J stated that:
    “the "purpose [of the Overage Provision] does not matter. Whatever the reason for entering the overage covenant (and each side may have had a different reason) it is the legal obligation itself ("the Overage Provision") which must be given effect.”

Comment

Although the case turned on its own facts, the long and complex judgment illustrates the difficulty of interpreting what is meant by using reasonable endeavours in a complex development situation. The case also shows the problems that will result where a party which may be required to make an overage payment has substantial control over the achievement (or otherwise) of the trigger for payment of that overage. As Norris J. said in the first paragraph of his judgment: “How hard do you have to work to make yourself liable to pay £1.4 million?”

Back to top
If you have found this page useful, you may be interested in the following:

Options
Free Summaries £nil
Full Membership From £207 + VAT (1 year)